| Quote Number | QUO-477 |
| Quote Date | September 24, 2021 |
| Valid Until | October 14, 2021 |
| Total | RM20,000.00 |
Project ZTS System - Take Over + Debug:
System development shared by the external vendor (51feijin - 广州飞进信息科技有限公司), completion of the system = unknown.
Source codes and technical general guidelines received via email (NOT included system proposal), downloaded, but code functionality = unknown.
As per the client request ultra urgent (to launch by the end of October, launch on 1st November), the strategy is as below:
Pre-requisite = Phase 1 Completion
https://vip.jagole.com/j_quote/zts-system-take-over-debug-phase-1/
Phase 2
*Discount is given as we shall leverage existing setup as much as possible without making any migration/transfer to avoid further amendment that will consume more time
IMPORTANT NOTES:
| Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
|---|---|---|---|---|
| 1 | Part 4: Review code and flow (as fast as possible) *fees are not included with major modification IF major flaw found from existing developed system |
RM20,000.00 | 0.00% | RM20,000.00 |
| Sub Total | RM20,000.00 |
| Tax | RM1,818.18 |
| Total | RM20,000.00 |